Net MeteringMSEDCLMaharashtra Policy

MSEDCL Net Metering in Pune: Process, Timeline & Documents (2026)

Mr. Shantanu Mustare· 6 min read

What Is Net Metering?

Net metering lets your rooftop solar system offset your electricity bill by feeding surplus power back to the grid. During the day, your solar panels power your home first; any excess is exported to the MSEDCL grid through a bi-directional meter, and you're billed only on the net units you draw over the billing cycle.

Net metering vs gross metering

  • Net metering: Solar first serves your on-site load; only surplus is exported. You pay for net units consumed. This is what most residential and small commercial consumers in Maharashtra use.
  • Gross metering: Your entire solar output is exported to the grid at a fixed feed-in tariff, and your consumption is billed separately. Used in specific segments and larger systems.

In Maharashtra, net metering is currently available for residential rooftop systems up to 10 kW under MERC regulations.

The MSEDCL net metering process

  1. Online application: Submit your site, load and proposed system details to MSEDCL.
  2. Technical feasibility approval: MSEDCL verifies your connection and local transformer capacity can support the system. Systems above 3 kW may involve additional verification.
  3. Installation: An empanelled EPC installs the system once feasibility is cleared.
  4. Inspection: DISCOM/CEI inspection where applicable.
  5. Net meter installation & commissioning: MSEDCL installs the bi-directional meter and synchronises your system — usually within about 10 working days of the testing request.

Typical timeline in Pune

For a straightforward residential system with documents in order, the end-to-end process usually completes in a few weeks. Feasibility approval alone is typically 7–15 working days in Pune's urban circles; rural circles can take longer.

Documents required

  • Latest MSEDCL electricity bill (consumer number + sanctioned load)
  • Identity and address proof (Aadhaar / PAN)
  • Proof of property ownership or owner's consent
  • For housing societies / shared roofs: a society NOC

Things to watch in Maharashtra

  • Your system capacity should generally not exceed your sanctioned load — a load enhancement may be needed otherwise.
  • Connections of 10 kW and above fall under Time-of-Day (TOD) tariff billing under the Electricity (Rights of Consumers) Rules.
  • Systems above 10 kW may move to net billing / gross metering and can attract grid-support charges. We model the best configuration for your consumption before you commit.

How Raymax Solar helps

Raymax Solar handles the paperwork, system drawings, inspection coordination and final commissioning on your behalf as an empanelled integrator — so your net-metering application moves through MSEDCL smoothly and your system is synchronised correctly the first time. Homeowners can also read our PM Surya Ghar subsidy guide for Maharashtra to understand the residential application journey.